Step #1 October 29, 2007 Property Cleaned up
Step #2 November 1, 2007 Cement Contract approved for one 25ft x 40 ft basketball slab and one 16ft x 20 ft picnic table slab. (Waiting for Basketball goal for installation)
Slab poured
Step #3 One Heavy duty basketball goal (on order,Nov 5th, 7-10 days)on hand assembled
Step #4 Estimated cost for three picnic tables (one ADA) and one park grill approximately Sent to HOA Office/ordered 11/7/2007. Delivery 2/4 weeks.Arrived need assembling
Pending:
Crushed granite walkway Pending payment
Playground Set
Jim