Work during the month of June involved the installation of underground pipelines and the construction of the embankments for 136th Avenue and the northbound I-25 ramps. In july the contractor will perform night work on I-25 with two of the three lanes closed to place concrete barrier to protect workers working to widen I-25 for a short length. This widening will provide the space needed so that the center pier supports for the bridge can be constructed with very little interference to the flow of traffic. For more information, go to: http://www.i-25at136ave.com/.