Here is a list of various T-REX activities scheduled for next weeks----
o Concrete paving for the new northbound I-25 lanes from Logan to University began last week and will continue this week.
* Work on the Downing St. off-ramp from northbound I-25 will be continuing, with grading, drainage and walls.
* The weekend of 15-18 (postponed from weekend of April 8-11) - University Blvd and the ramps to and from I-25 will close on Friday night at 8 p.m. and re-open Monday morning at 5:30 a.m. in a new lane configuration. During this weekend closures, NB University Blvd motorists will be directed to use Evans Ave to Colorado Blvd and SB University Blvd motorists will be directed west on Louisiana Ave to Franklin St and south on Franklin to S. Buchtel back to University. The ramps to and from I-25 at University will also be closed and motorists should use Colorado Blvd. These closures are for drainage work and the traffic shift.
* Monday, April 18 - University Blvd. will have one lane in each direction from Iowa Ave. to Asbury Ave. It will stay in this configuration until Fall 2005.
* There will continue to be work on the soundwalls up and down the corridor.
* Sunday, April 10 - The SB I-225 to SB I-25 ramp and tunnel will be closed during the early morning hours of midnight until 5:30 am for bridge work. Motorists should exit at DTC Blvd; go south to Belleview, then east on Belleview to SB I-25.
* Sunday, April 10 - Thursday, April 14 - The Yosemite on-ramp to NB I-225 will be closed from 9 pm until 5:30 am the next morning. Motorists should use DTC Blvd.
* Sunday, April 10 - Thursday, April 14 - The Yosemite off-ramp from SB I-225 will be closed from 9 pm until 5:30 am the next morning. Motorists should use DTC Blvd.
* Sunday, April 10 - Thursday, April 14 - There will be various closures at the Arapahoe Rd interchange including ramps. Closures will start at 9 pm and will open by 5:30 am the next morning. Crews will be doing grading work during these closures
* Weekend of April 22-24 - There will be lane restrictions at the Yosemite St and Caley Ave. intersection for storm drain work. The lane restrictions will be from 8 a.m. until 7 p.m.
* Sunday, April 10 - Thursday, April 14 - There will be lane restrictions on Dry Creek Rd for landscaping work.
* Weekend April 15-18 - The on-ramps to SB I-25 from EB & WB County Line Rd will be closed. Motorists will be directed to access SB I-25 from Lincoln Ave. or Dry Creek Rd.
* Throughout the week there will various lane closures on I-25 and I-225 for grading, paving and bridge work.
* As weather permits, crews will continue working on freshening the lane striping and repairing potholes up and down the corridor.
All of these activities are weather dependent; please check the 24-hour information line at 303-786-TREX or the Web site at www.trexproject.com for the most current information.
Hunter Sydnor
Public Information T-REX
303-357-8677
hunter.sydnor@seccteam.com
Here is a list of various T-REX activities scheduled for next weeks----
* Sunday, April 3 - There will be a full closure of NB and SB I-25 from Hampden Ave to Santa Fe Dr. The closure will begin at 9 pm and all lanes will be open by 5:30 am Monday morning. The detour will be Hampden to Santa Fe. This closure is for a traffic shift under Colorado Blvd.
* Wednesday & Thursday, April 6 & 7 - There will be a full closure of NB and SB I-25 from Hampden Ave to Santa Fe Dr. The closure will begin at 9 pm. On Wednesday night the SB closure will begin 1 hour after the Rockies Game. All lanes will be open by 5:30 am the next morning. These closures will allow crews to erect the girders for the Colorado Blvd Bridge. The detour will be Hampden to Santa Fe.
* Crews are continuing to work on walls and grading in preparation for paving of the new northbound I-25 lanes later this spring.
* Work on the Downing St. off-ramp from northbound I-25 will be continuing, with grading, drainage and walls.
* The weekends of April 1 - 4 & April 8-11- University Blvd. will be closed under I-25 for 2 weekends - April 1 - 4 and April 8-11. University Boulevard, the ramps to and from I-25 will be closed. Closures will begin at 9 p.m. on Friday night and all lanes will be open by 5:30 a.m. Monday morning. During these weekend closures, northbound University Blvd motorists will be directed to use Evans Ave. to Colorado Blvd. and southbound University Blvd. motorists will be directed west on Louisiana Ave. to Franklin St. and south on Franklin to S. Buchtel. The ramps to and from I-25 at University will also be closed and motorists should use Colorado Blvd. These closures are for drainage work and a traffic shift.
* Monday, April 11 - University Blvd. will have one lane in each direction from Iowa Ave. to Asbury Ave. It will stay in this configuration until Fall 2005.
* There will continue to be work on the soundwalls up and down the corridor.
* Tuesday, March 29 - The SB I-225 to SB I-25 ramp and tunnel will be closed during the early morning hours of 1 am until 5:30 am for bridge work. Motorists should exit at DTC Blvd; go south to Belleview, then east on Belleview to SB I-25.
* Sunday, March 27 - The Parker Rd on-ramp to SB I-225 will be closed for grading work. The ramp will be open by 5:30 am Monday morning. Motorists should access SB I-225 at Iliff Ave.
* Monday, March 28 - The Yosemite on-ramp to NB I-225 will be closed for grading work. The ramp will be open by 5:30 am Tuesday morning. Motorists should access NB I-225 at DTC Blvd.
* There will be various nighttime closures on Ulster St. and DTC Blvd. under I-225 for work on the bridges. Closures will begin at 9 p.m. and re-open by 5:30 a.m. the next morning. There will also be lane closures during the day.
* Monday, March 28 - The Belleview Ave off-ramp from NB I-25 will be closed for paving work. The ramp will be open by 5:30 am Tuesday morning. During this overnight closure, motorists should exit NB I-25 at Orchard Rd.
* Monday, March 28 - Thursday, March 31 - There will be various closures at the Arapahoe Rd interchange. Closures will start at 9 pm and will open by 5:30 am the next morning and include the off-ramp from southbound I-25, the on-ramps to northbound and southbound I-25 from eastbound Arapahoe Rd. and the on-ramp to southbound I-25 from westbound Arapahoe Rd. Crews will be doing grading work during these closures
* Monday, March 28 - The Dry Creek Rd. off-ramp from NB I-25 will be closed beginning at 8:30 pm for grading work. The ramp will be open by 5:30 am Tuesday morning. During this overnight closure, motorists should exit NB I-25 at Arapahoe Rd or County Line Rd
* Monday, March 28 - The Dry Creek Rd. on-ramp to SB I-25 will be closed beginning at 10 pm for grading work. The ramp will be open by 5:30 am Tuesday morning. During this overnight closure, motorists should access SB I-25 at Arapahoe Rd.
* Monday, March 28 - The EB and WB County Line Rd on-ramps to SB I-25 will be closed beginning at 10 pm for paving. The ramps will be open by 5:30 am Tuesday morning. During this overnight closure, motorists should use Lincoln to access SB I-25
* Throughout the week there will various lane closures on I-25 and I-225 for grading, paving and bridge work.
* As weather permits, crews will continue working on freshening the lane striping and repairing potholes up and down the corridor.
All of these activities are weather dependent; please check the 24-hour information line at 303-786-TREX or the Web site at www.trexproject.com for the most current information.
Hunter Sydnor
Public Information T-REX
303-357-8677
hunter.sydnor@seccteam.com
Here is a list of various T-REX activities scheduled for next weeks----
* Sunday, March 13 - There will be a full closure of northbound I-25 from Hampden Ave to Santa Fe Dr. The closure will begin at 9 pm and all lanes will be open by 5:30 am Monday morning. The detour will be Hampden to Santa Fe. This closure is for a traffic shift under Colorado Blvd.
* Wednesday, March 16 - There will be a full closure of southbound I-25 from Santa Fe Dr to Hampden Ave. The closure will begin at 1 am and all lanes will be open by 5:30 am. The detour will be Santa Fe to Hampden. This closure is for a traffic shift under Hampden Ave.
* Crews are continuing to work on walls and grading in preparation for paving of the new northbound I-25 lanes later this spring.
* Work on the Downing St. off-ramp from northbound I-25 will be continuing, with grading, drainage and walls.
* March 19, March 25 - 28 & April 1 - 4 - University Blvd. will be closed under I-25 for 3 weekends - March 19, March 25 - 28 and April 1 - 4. University Boulevard, the ramps to and from I-25 and the South Buchtel Boulevard interchange will be closed for the day on Saturday, March 19 from 7 a.m. to 7 p.m. The weekends of March 25 and April 1, the closures will begin at 9 p.m. on Friday night and all lanes will be open by 5:30 a.m. Monday morning. During these weekend closures, northbound University Blvd motorists will be directed to use Evans Ave. to Colorado Blvd. and southbound University Blvd. motorists will be directed west on Louisiana Ave. to Franklin St. and south on Franklin to S. Buchtel. The ramps to and from I-25 at University will also be closed and motorists should use Colorado Blvd. These closures are for drainage work and a traffic shift.
* Monday, April 4 - University Blvd. will have one lane in each direction from Iowa Ave. to Asbury Ave. It will stay in this configuration until Fall 2005.
* There will continue to be work on the soundwalls up and down the corridor.
* Monday- March 14 - Crews will be doing utility locates during the day on Yale Circle and Yale Ave.
* Monday March 14 - Friday, March 18 - The SB I-225 to SB I-25 ramp and tunnel will be closed during the early morning hours of 1 am until 5:30 am for bridge work. Motorists should exit at DTC Blvd; go south to Belleview, then east on Belleview to SB I-25.
* Monday March 14 - Friday, March 18 - The NB I-25 to NB I-225 ramp will be closed during the early morning hours of 1 am until 5:30 am for bridge work. Motorists should exit at Belleview; go east to DTC Blvd, then north on DTC to NB I-225.
* Sunday, March 13 - Thursday, March 17 - Ulster St. under I-225 will be closed for work on the bridges. Ulster will close at 9 p.m. each night and re-open by 5:30 a.m. the next morning.
* Monday, March 14 - Friday March 18 - There will be lane restrictions on Yosemite St. at Caley Ave. for drainage work during the day.
* Saturday, March 19 - Sunday, March 20 - There will be lane restrictions on Yosemite St. at Caley Ave. for drainage work.
* Sunday, March 13 - Thursday, March 17 - The Orchard Rd. on-ramp to northbound I-25 will be closed for grading work. The ramp will close at 8 p.m. and re-open the next morning at 5:30 a.m.
* Monday, March 14 - Thursday, March 17 - The Arapahoe Rd off-ramp from SB I-25 and the WB Arapahoe Rd to SB I-25 on-ramp to SB I-25 will be closed at night for grading work.
* Tuesday, March 15 - The ramp from EB 470 to SB I-25 will be closed at night for barrier work. Motorists will be directed to go north on I-25 to Dry Creek Rd, exit and re-enter SB I-25.
* Throughout the week there will various lane closures on I-25 and I-225 for grading, paving and bridge work.
* As weather permits, crews will continue working on freshening the lane striping and repairing potholes up and down the corridor.
All of these activities are weather dependent; please check the 24-hour information line at 303-786-TREX or the Web site at www.trexproject.com for the most current information.
Hunter Sydnor
Public Information T-REX
303-357-8677
hunter.sydnor@seccteam.com