The Alma School Road project consists of the removal and replacement of the existing asphalt pavement on Alma School Road from Baseline Road to Southern Avenue. Also included in the project are the installation of new sidewalk ramps to meet current standards as well as miscellaneous concrete repair and replacement of damaged sidewalks, curbs, gutters, and driveways. This project is currently scheduled to begin on June 3 and be completed in 30 to 45 days.

 

The contractor will work to minimize disruptions to traffic on this section of roadway and will maintain access to local businesses. Below is a list of traffic restrictions on Alma School Road during this project:

 

 

June 3 to June 6

Minor disruptions and barricading in the curb lanes for concrete work

 

June 6 to June 16

Baseline to US 60 - 1 lane open in each direction US 60 to Southern - 2 lanes open in each direction

 

June 17 to June 26

Baseline to US 60 - 2 lanes open in each direction during peak times. Other times only 1 lane open in each direction.

US 60 to Southern - 2 lanes open in each direction

 

June 27 to June 29

Ramps to US 60 will be closed at night for paving in the interchange with US 60

 

June 30 to July 1

Baseline to US 60 - 2 lanes open in each direction US 60 to Southern - 2 lanes open in each direction

 

July 2 to July 5

Baseline to US 60 - 1 lane open in each direction US 60 to Southern - 2 lanes open in each direction

 

 

During freeway ramp closures, traffic to and from the freeway will be detoured to Dobson Road and Country Club Drive.

 

Should the schedule of traffic restrictions be changed, updated information is available on the City's Web site at

 