The May - Lecta - Sweet Neighborhood Association

Park ETA

Posted in: Legacy Pointe
Do we have an ETA on the completion/opening day of the park? I know all this rain doesn't help the progress but I never drive down that way and was curious how it's coming along.

By Lee Family
Park Update

Here's a recent update on Harmony Pointe Park from Kay Curry:


Harmony Pointe Park construction is progressing well. The construction of Phase I includes the playground, pavilion, bicycle rack, and sidewalks. Phase I does not include the basketball court or landscaping. Unfortunately there is no funding for these items at this time. The current construction should be completed by August. However, if the contractor continues at the present rate they will finish early. The Parks and Recreation Department host a grand opening for each new park and will be hosting one for Harmony Pointe. It is not scheduled at this time.

The City of Fayetteville Parks and Recreation Department has a Tree Donation Program that your POA may be interested in. I know trees are important to your Neighborhood. I am attaching information about this program.

I hope this information is helpful. If I can be of further assistance, please let me know.

Kay Curry, ASLA
Park Planner
kacurry@ci.fayettev ille.ar.us
(479)444-3472

Parks and Recreation
City of Fayetteville
113 West Mountain St.
Fayetteville, AR 72701


By Bob Law
Park Pictures

I've added some pictures to the main page:

http://www.neighborhoodlink.com/pdf/nhextra/580090007/754118365/529623794.pdf

By Bob Law
Advertise Here!

Promote Your Business or Product for $10/mo

istockphoto_1682638-attention.jpg

For just $10/mo you can promote your business or product directly to nearby residents. Buy 12 months and save 50%!

Buynow